The refurbishment of the public toilets is due to begin mid July 2008.  The work is scheduled to be completed within 14 weeks.  The contractors will require some working space on the car park so an area 6m x 11m has been allocated on the northern boundary immediately adjacent to the existing toilet block.

Temporary portaloos are to be provided and these will be positioned to the east of the working space, again along the northern boundary of the car park.  There will be two female and two male toilets and a cleaning contract has been arranged.

Clearly there will be some disruption to the car park whilst this work is in progress and residents are asked to be patient for the short term so that we can achieve the more long term improvement. Thank you.

                                                                                     Dorothy Waterworth                                                                        (Parish Clerk)

                                                                                             2 July 2008

             

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 